Showing posts with label A55. Show all posts
Showing posts with label A55. Show all posts

Wednesday, 15 February 2023

Re-blog: Improving links between North West England and North Wales

A version of this article was published in Rail Magazine in December 2021

As someone who lives on the Wirral and frequently travels to North Wales via the A494 through Queensferry, and has been a committee member of the Wrexham-Bidston Rail User's Association for a number of years, I'm well aware of current poor transport connections between North West England and North Wales. The bridge which carries the A494 over the River Dee and on to the A55 was used by 60,000 vehicles a day before the Pandemic. So, knowing how busy the A494 can get, particularly during school holidays and on Fridays before bank holidays when people flock to North Wales, I supported a proposal to build a new link road from the A548 Flintshire bridge to the A55, a proposal known as the "Red Route".

You may be wondering what if anything roads have to do with railways? Well, recently my support for the "Red Route" has started to wane, especially as awareness of the climate emergency has grown. However despite the pandemic, the A494 often still gets incredibly congested and in 2020 particularly with many people holidaying in the UK, it seemed as if the A494/A55 was busier than ever. Even so, the Welsh Government may be right to cancel the "Red Route". But it does beg the question, how are the aims of the Union connectivity review which was published in December 2021 going to be delivered if not by upgrading road connections? The report led by Sir Peter Hendy sought to identify ways of improving connectivity between the 4 UK nations and recommended that the Westminster works “with the Welsh Government to undertake a multimodal review of the North Wales transport corridor”

The four-lane bridge which carries the A494 over the River Dee is set to be replaced, with work due to begin in 2024/25 and as the proposal falls under renewals is not subject to the same environmental review as the Red Route. The bridge replacement will see an additional lane in each direction added to the A494 which may relieve congestion in the short term. However, the only long-term solution to improve links would be to build the new link road to the A55.

Map showing the road and rail links between England and North Wales

If new roads aren't the answer then the only other alternative is to improve rail links between the two nations, which are the North Wales Coast Line, the Wrexham-Bidston (Borderlands) Line and Shrewsbury-Chester Line. The latter was recently partially re-double between Chester and Wrexham General, however, the Wrexham-Bidston and North Wales Coast Line are in dire need of upgrades and are currently underutilised. The hourly Transport for Wales service from Manchester to North Wales is often crowded and fares are relatively expensive, also the hourly service on the Borderlands Line isn't viewed as a reliable means of travelling between North East Wales and Liverpool.

North Wales Coast services will be given a boost in December 2023 when TfW plans to introduce an hourly Liverpool to Llandudno service which will use new Class 197 DMUs that are now being introduced. The CAF-built units are being introduced on TfW's long-distance service, such as Manchester to Llandudno Junction and Manchester to South Wales. The introduction of Class 197s and rakes of Mk4 carriages will allow TfW to operate five-car trains between Manchester and South Wales, but TfW is yet to decide if the new stock will allow the operator to improve capacity between Manchester and North Wales. If passengers travelling between Manchester and North Wales are to benefit from the introduction of new units then TfW must operate more four-car (2x2) or three-car services as a minimum. Even in this post-pandemic era, operating two-car trains between Manchester and North Wales is simply unacceptable.

Class 197 002 on display at Chester Station

TfW also plan to introduce a new Liverpool to Shrewsbury via Wrexham General service from December 2024, which will be extended to Cardiff every two hours. The Liverpool to Shrewsbury will be an extension of the current Liverpool to Chester via Halton Curve service and be coupled to the Llandudno service as far as Chester, where the two units will split, with one unit going to Llandudno, whilst the other travels to Shrewsbury/Cardiff. The Llandudno service is set to begin in December this year (2023), whilst the Shrewsbury/Cardiff service isn't due to commence until December 2024 and is subject to capacity improvements being completed between Wrexham and Shrewsbury.

As well as improved connectivity between Liverpool and North Wales the new service to Llandudno will also improve connectivity at Shotton, as currently, only one North Wales Coast service per hour calls at Shotton low-level and one Borderlands Line train per hour calls at high-level. With two trains per hour calling at both high-level and low-level the interchange possibilities between the two lines will be vastly improved.

Whilst the Borderlands line isn't currently viewed as a reliable means to travel between Liverpool and NE Wales, the line will hopefully see improvements as the delayed increase in the frequency of the service from one, to two trains per hour is finally set to begin this year. Thankfully the ORR has settled the dispute between TfW who wanted to increase the frequency and GBRf who wanted more freight paths into the cement works at Padeswood. However, a proposed compromise will see gaps in the half-hourly service during the day to allow freight movements into and out of Padeswood. 

The only thing holding up the half-hourly service now is the entry into service of the much-delayed Class 230s, which have been dogged by technical issues, the Pandemic and last year the unit's manufacturer going into administration. However, TfW who owns the Class 230s seems to have come to an agreement regarding maintenance and Class 230s which have once again started driver training on the line. In addition to the gaps during the day, the additional service will be a skip-stop service and will cut out a number of stations between Gwersyllt and Shotton. This isn't to do with freight however, but based on concerns about hitting a specific reliability target, as the turnaround of the current service is already very tight.

The interior of Class 230 which was converted from redundant D78 stock

In the long term groups such as the WBRUA and Growth Track 360 would like to see four trains per hour operating from Wrexham directly through into Liverpool and if the trial of the battery variant of the Class 777 is successful, then this may be a real possibility. This could be quite expensive, as it would require additional infrastructure, such as rapid charging via 3rd rail at the Wrexham end of the line, the installation of additional block sections, particularly between Penyffordd and Dee Marsh and of course additional battery Class 777s IPEMUs (independently powered electrical multiple units) to be ordered.

Class 777 002 on display at Rail Live

Providing additional capacity is one thing, but fare prices may also be a barrier for many people and there does seem to be a disparity between the cost of fares offered by TfW and other TOCs, and between North and South Wales. In 2019 a BBC investigation found that it cost 41p per mile to travel from Flint to Bangor, in contrast, it cost just 27p per mile to travel from Swansea to Cardiff Central. I believe strongly that somehow prices need to be reduced and simplified for passengers travelling between NW England and N Wales in order to drive any meaningful modal shift from road to rail.

Returning to the UCR, the document itself seems to be lacking in detail and there doesn't appear to be any concrete plans for improving cross-border links, instead, it suggests that Westminster and the Welsh Government should investigate ways of improving connectivity. Very little attention is given to freight but does recognise the importance of the M56, A494 and A55 and the link they provide to the port of Holyhead, which moved 5.3 million tonnes of freight and 1.9 people between the mainland and Dublin in 2019.

Brexit will undoubtedly continue to have an impact on EU freight travelling between ports in the east of England to Dublin via Holyhead, but the port will remain an important and heavily used link between the mainland and Ireland. In my view, the DfT should explore options for providing container handling facilities near to the port to reduce HGV traffic travelling from England to Holyhead. That way at least freight could be transported to Holyhead by rail and then transferred to HGVs which can then be loaded onto ferry services. Building a container port at Holyhead would possibly be a better solution, but ultimately not easily achievable.

One thing is clear if more capacity is to be provided for passenger and freight services then the North Wales Mainline should be electrified and signalling upgraded. It's unlikely that there would be much capacity for additional services beyond those already proposed by TfW and Avanti. Electrification also provides the potential for HS2 classic compatible services to use the North Wales Coast Line, rather than the current proposals which would see passengers from North Wales having to change trains at Crewe to access HS2 services heading to the capital. Although it should be pointed out that even with the interchange at Crewe passengers from North Wales could still see a significant reduction in journey times for N Wales to London when compared to direct services via the WCML.

It does finally appear as if improved rail links between NW England and N Wales are on the horizon, but I do not believe the current pipeline of improvements on their own will be enough to have any meaningful impact on thousands of daily trips made by car between the two nations. I believe that much more investment will be needed to further improve rail links combined with a review of fares to try to simplify and bring down the costs in order to drive the considerable shift from road to rail that is needed if the UK is to achieve its net-zero goals.

Wednesday, 13 February 2019

Northern Gateway, Deeside

Progress is finally beginning to be made on the multi-million pound Northern Gateway scheme for which outline planning permission was first granted for housing development, a hotel and technology park back in 2013.

Since then the only visible sign of progress was the completion in 2016 of an access road leading from the B5441 Welsh Road, for which £3.1m was awarded by the Welsh Government. Since then it appeared as if the project had stalled and the road sat unused, however work to clear the land ready for development is now well underway.

A key part of the North Gateway scheme is a 140-acre development lead by Praxis Real Estate Management Ltd. The scheme has outline planning permission for the development consisting of B2 general industrial units and B8 Storage or distribution units, with industrial units ranging in size from 50,000 sq ft up to 1,000,000 sq ft.

[click to enlarge] 

D Morgan PLC which had previously constructed the link road is now the principal contractor for The Airfields development and has already begun work to clear the site. The image below shows the scale of the works that has already been undertaken.

[click to enlarge] 


As well as The Airfields development, detailed proposals have also been submitted by developer Pochin to build 134 houses on the former Corus steelworks site located in Garden City. It is proposed that a total of 725 homes will be constructed over a period of 9 years on the site.

If the full scope of the Northern Gateway development can be realised it is hoped that 5000 jobs will be created in total. If this is to be achieved it is vital that transport links to Northern Gateway and Deeside Industrial Park are improved.

[click to enlarge]  

So far it has been announced that “Red Option” which aims to reduce congestion on the A494 to A55 corridor has been chosen to be taken forward to the planning phase. Enhancements along the A548 and a new section of road to be constructed connecting the Flintshire bridge to the A55 will vastly improve the vital link to Holyhead and help to reduce congestion on the section of the A494 known as Drome Corner leading to Aston Hill.

Plans to improve public transport are also being explored with a proposal put forward to improve Hawarden Bridge station on the Wrexham Bidston line which would serve the Garden City/Corus steelworks development. In addition, plans have been taken forward to explore the feasibility of building a new station on the Wrexham Bidston line that would serve the Deeside Industrial Park

The new station known as Deeside Parkway would be located near to the UPM paper mill and Great Bear distribution centre. If the new station was constructed not only would it provide access for workers from the Wirral and North East Wales to access the Deeside Industrial Park, but it could also serve as a park and ride facility for residents from Flint and Connah's Quay who wish to travel by rail to Liverpool, which has the potential to reduce congestion on the Welsh road leading to the M53. The provision of shuttle buses to serve the Deeside and Garden City areas area are also being considered as part of a wider public transport strategy.

If the plans can be delivered in conjunction with improvements to road and rail links then Northern Gateway has the potential to have far-reaching economic benefits and provide employment not just North East Wales but also the Wirral and Cheshire West. I hope to able to follow the development over the coming years.

[click to enlarge] 

Wednesday, 19 July 2017

A494 to A55 improvement proposals (part 2)

A494 - A55 Red option

In the first part I described some of the background into the previous attempt to upgrade the A494/A55 corridor, in this second part I will explain in more detail the "Red option" which is currently preferred by the Welsh Government.

The Red option involves construction of roughly 3.5km of new dual carriageway between the A548 and the A55. The proposal also involves grade separating a number of roundabouts along the A548 which provide access to the Deeside Industrial Park.

A494 looking south toward the A550 interchange and Deeside Industrial Park

Although the Red option primarily involves the construction of a new road, there will be some major works involving interfaces with existing roads. A new junction will have to be constructed on top of the junction where the A550 meets the A494, a junction that itself was only completed in 2009. 

Proposed A550/A494/A548 interchange (Click to enlarge)
Image for demonstrative purposes only, not to scale. Alignment is subject to change. 

It appears as if the new junction will be construction so that the A494-A548 route will be the main route to the A55. I assume that signage and lanes will have to be marked in such a way to direct people travelling from England wishing to access the A55 for Wrexham/Chester/Mold via the A494 and those wishing to access the A55 for the North Wales Coast/Anglesey/Holyhead via the new A548 link.

The A548 at the point where it passes the Deeside Industrial Park will be mostly re aligned with the existing carriageway alignment used for exit/entry slips between the new carriageway and roundabouts.

The dumbbell junction on the A584 for Connah's Quay will also have to be relocated as the carriageway will be re aligned to head North West towards the A55. The section of dual A584 currently ends 500 metres after the junction for Connah's Quay. After that the A548 becomes a single carriageway. The current A548 route does eventually meet the A55 but not until it reaches Pensarn some 38km away.

It will be interesting to note if or how the new A584 - A55 link is numbered if it is constructed.



The Welsh government have identified journey time benefits as one of the main benefits of the Red option over that of the Blue option. However there are other potential benefits, such as supporting the case for a new railway station that is proposed within the Deeside Industrial Park on the Wrexham Bidston railway line.

Proposed Deeside Parkway station, image courtesy of the Wrexham-Bidston Rail Users' Association

It is envisaged that the new station as well as providing access to the industrial park for workers, could also provide park and ride facilities for those travelling from Wales wishing to travel to Liverpool. Rather than driving to Liverpool of Hooton station (on the Merseyrail Wirral line), people could park at and travel from Deeside Parkway.

The other obvious benefit over the Blue option is the fact that a lot of the construction will be off the main carriageway. The Blue option involves working on the live carriageway at a point where congestion is already at its worst.

The Red option also provides a diversionary route if problems arise, concurrently the existing A494 would provide access to North Wales if there were problems on the A548. Currently in reality there is only one main route into North Wales and that is the A494-A55 corridor.

Another element to take into consideration is the replacement of the  A494 Dee bridge "which is in a poor structural condition"[1], there are already separate plans being put into place to replace the existing steel and concrete bridge. Replacing the bridge during or after potentially upgrading the A494 would bring with it further disruption. The Red option would at least provide a diversionary route whilst a new bridge is being built.


A decision is expected this year on whether to go ahead and if so which route to progress, so we won't have long to wait. In the meantime you can see how each of the options would look thanks to videos produced by the Welsh Government.



Follow us on Twitter and Facebook - For more information e-mail Blog@EngineeringFocus.co.uk




Monday, 17 July 2017

A494 to A55 improvement proposals (part 1)

[Update 26/09/17]

"Economy Secretary Ken Skates has today announced the red route as the preferred option for the £250m Deeside corridor scheme." View the full statement at www.gov.wales

Background 

After a decade of delay the Welsh Government looks set to finally make a decision on how best to improve a vital link between England and Wales. The A494 - A55 link is one of the busiest border crossings between England and Wales, with the 2 lane A494 at the point where it crosses the River Dee alone carrying almost as many vehicles as the 3 lane M4 Second Severn Crossing [1][2]

The first plans to improve the link were put forward in 2007 by which time houses had already been compulsorily purchased and to this day many remain empty. The original proposal was for a 7 lane highway consisting of 4 southbound lanes (heading toward Wales), 3 northbound lanes (heading towards England) with hard shoulders and connector distributor roads either side. It was also proposed that the speed limit would be increased from 50mph to 70mph.

Existing A494 at the point where it crosses the River Dee


Just as the proposal looked to go ahead and with the majority of the land already in government hands the plans were scrapped after fierce public opposition. It was said the proposal which in places would be 11 lanes wide were excessive and disrupted too many people. It was claimed that 5000 people would be adversely affected.

The decision to cancel the proposal as it stood at the time may have had merit, unfortunately though the Welsh Government were slow to come up with an alternative and in the proceeding 10 years traffic levels have increased and congestion between the A494 and A55 has worsened, especial during holiday periods.

New proposals

Two proposals have been put forward by the Welsh Government, one known as the Blue option an adaptation of the original proposal to widen the A494 and upgrade junctions including the  A494/A55 interchange.

The other proposal known as the Red option would bypass a large section of the A494 and the A494/A55 interchange. This would be achieved with the construction of a new section of dual carriageway between Flintshire bridge and the A55 close to junction 33 near to Northop. The flat junctions along the A548 which links A494 to Flintshire bridge would also be grade separated.

Proposed Red and Blue options (source  Deeside Corridor improvement study)


The public consultation for both proposals ended on the 30th of June 2017 with the preferred route expected to be announced this summer. However the Welsh government has already signalled that it prefers the second opinion or what is known as the Red Option. Both options would have a budget of around £200m, however the Red option promises a better benefit to cost ratio and improved journey times.

The A548 Flintshire Bridge


On a more symbolic note, the Red option would see the realisation of a long talked about link from Flintshire bridge which for the last two decades has been known locally as "the bridge to nowhere" to the A55.


The consultation document can still be found here.


Part 2 of the blog descibes the Red option in more detail


Follow us on Twitter and Facebook - For more information e-mail Blog@EngineeringFocus.co.uk





Latest blog post

HS2 Bridges and Viaducts Engineering Challenges

A version of this article was published in RAIL Magazine issue 1040 Construction of the 220km (140 mile) long HS2 route between London and ...