Sunday, 15 June 2025
Midlands Rail Hub
Monday, 15 November 2021
Building HS2 - Curzon Street and Interchange progress.
Update 15/11/21
It would seem that the title of the blog should have been "the time for discussion should be over" as it appears the leg from Birmingham to Leeds is going to be heavily curtailed. I'll wait and see what detail emerge this week, but it seems almost certain that the government is going to be making a huge mistake. Not only will de-scoping HS2 East reduce the journey time benefits from Leeds to London and Birmingham, and mean there will be little to no increase in capacity, but it will also mean that there will be no hope of improved regional journeys that would have been made possible by the construction of the eastern leg of HS2.
In 2009 when I first began actively campaigning in support of HS2 I never imagined I'd one day be photographing and writing about the construction of the project. At the time I was in my mid-20s and full of youthful optimism and felt that someone ought to be challenging the many myths about the project which were being disseminated by opponents of the project. At the time HS2 Ltd had no social media presence and no one working for the DfT felt it was the job of HS2 Ltd or indeed Government to promote the project. HS2 Ltd's job was solely seen as designing the line and ensuring the required bills made their way through parliament.
In the end HS2 took 10 years to get from the initial planning phase to construction, but finally in June this year (2021) I captured my first images of the progress so far. Admittedly I'm a little late to the party, as construction has been underway for quite some time, in fact, the first TBMs christened Florence and Cecilia launched to dig the two 10 mile long tunnels underneath the Chiltern hills have already excavated 2 miles of tunnels between them. However the pandemic and living up North made it difficult to justify a trip south just to see what's been going on. So, during my visit to the Midlands for Rail Live 2021 I thought I'd have an extended stay so I could see for myself some of the progress that has been made so far on the construction of HS2.
The first stop was the site of what will eventually be the HS2 Interchange station located close to Birmingham Airport. This station will be connected to Birmingham International railway station and Birmingham Airport using an automated people mover, which will be able to transport people from the station to the airport in just 6 minutes. Birmingham Interchange will also allow people from Solihull and the surrounding area to access HS2 services to London, Birmingham city centre and the North. The station itself will be comprised of 2 platforms, with 4 platform faces and a pair of through tracks for non-stopping services from the North to London.
A significant amount of work has already taken place around what will be the new station, with a key road bridge over the M42 having already been constructed. The 65-metre bridge which now spans the M42 was moved into place by SPMTs (Self-Propelled Modular Transporters) over the space of just 2 days. A new road bridge has also been installed over A446/A452 which will link the A452 to a new link road and roundabout to Birmingham Interchange and NEC, a video of which can be seen here
Preparatory works taking place on the site of new link roads and roundabout connecting the A452 and A446 to the new station and the NEC
The new link road bridge over M42.
Groundworks appeared to have started on the site of the new 400m long station, however, the tender to build the station itself isn't due to be awarded until next year, so it's unlikely that any significant progress towards construction will begin before the end of 2022.
First signs of groundworks taking place for Birmingham Interchange
The next day I took a trip into Birmingham to check out the site of another new station, this time located in the heart of the city. Curzon Street station is being constructed alongside the WCML and will have an entrance next to Moor Street station, and despite claims to the contrary made by opponents of HS2 will be only a few minutes by foot from Birmingham New Street station.
A video taken onboard a WMR service into Birmingham New Street station showing progress as of June 2021 can be found here.
Curzon Street station will be a 400m long station with 7 platforms, the main entrance of which will open out onto Moor Street Queensway providing access to Birmingham Moor St station, with a short walk through St Martin's Queensway to New Street station. There will also be a second entrance roughly in the middle of the station which will utilise the original building which formed the entrance to the former station which was the terminus of the London and Birmingham Railway and the Grand Junction Railway. The original station opened in 1838, but was closed to passengers in 1893, the station itself was later demolished but the Roman-inspired Grade I listed building survived. It is this building that has been incorporated into the design of Curzon Street station. The building which will form an entrance leading out onto Curzon Street is currently undergoing refurbishment. Once completed the building will include "a new steel structural frame to strengthen the building, a new lift giving access to all four levels, new glass balustrade for the historic staircase, internal fit-out, roof repairs, structural repairs to the external façade, and a full clean of the external building masonry." source HS2 Ltd
The original building which formed the terminus of the London and Birmingham Railway
There will be 3 departures from Curzon St to London each hour, taking just 45 minutes to reach the capital, stopping at Interchange and Old Oak Common. There will also be services to Manchester once HS2 phase 2b is complete, with the journey taking just 41 minutes, slashing the Birmingham to Manchester journey time in half. There are currently plans to operate services to Leeds once phase 2 East is completely, but there are currently questions over whether this phase will be built in full or not. If the section of HS2 to Leeds is built in full then the journey time from Birmingham to Leeds would be 49 minutes, cutting the journey time in half, down from 2 hours currently.
Komatsu excavator loading a Wacker Neuson Dual View dumper on the site of what will be Curzon Street station
Although there wasn't a great deal of construction to see during my visit to the West Midlands it was certainly good to see that some progress is finally being made after 10 years of discussion. Looking back at my 5 years of campaigning activity from 2009 I'm not sure what, if any impact I made, but I felt strongly at the time that someone should be challenging the myths from HS2 opponents. It's frustrating to see that although over 10 years have passed, some of the old tropes such it only saving 15 minutes are still being circulated, but despite the best efforts of a well funded and vociferous anti-HS2 campaign the line is being built and there's very little the current cohort of opponents can do but add to the cost, through the need for extra security and legal fees to force the removal of protesters.
For me, my brief foray into campaigning inspired a love of the railways which has stayed with me and has inspired me to continue campaigning, but now on more of a local level, which has seen me campaigning for improved rail links on the Wrexham-Bidston line.
I hope to be able to make it down the West Midlands and further south again to see how construction progresses on this monumental construction project.
Friday, 17 February 2017
Building a new North South railway - part 1 (update)
Update
The bill giving the go ahead to construct phase 1 of HS2 was given Royal Assent on Thursday 23rd of February.
This blog will focus solely on the construction and engineering involved, so I will leave a description of project and the political aspects of the planning to one side.
To begin with I want to explore how you go about altering the landscape in order to build a new high-speed railway that is as flat and straight as possible. With a maximum design speed of 400km/h (250mph) over the straightest sections of track it is important that the curve radius is long as possible, in the case of HS2 the minimum horizontal radius for 400km/h operation is 7200m.
Using knowledge gained from following other road and rail projects it's possible to examine how the new line will likely be built and the construction methods involved.
The closest recent parallel that I can draw upon is the construction of a new grade separated rail junction at Norton Bridge (Staffordshire), this project required the construction of 11 bridges and 9.6km of new railway.
Other parallels can be drawn from the construction of 7.5km of new dual carriageway connecting the M6 and M56 in Cheshire.
With both projects a large part of the work "simply" involved moving earth via moxy (articulated dump truck) from one part of the site to the other, although there was of course a systematic and very purposeful way in which this is done.
As with any large construction project the first stage will involve establishing compound sites along the route in which offices and staff facilities will be located and plant machinery stored.
Before any site clearance can commence the area within the site boundary must be free of protected species such as great crested newts for a number of weeks, during which time regular inspections must take place.
Once the site boundary is established (and free of newts) and compounds complete the next task is to begin preparing the land through which the line will be built. In rural areas this will involve stripping and storing the initial layer of fertile earth. The earth is stored close to where it was originally excavated from, this is so it can be returned back to the land once final landscaping commences.
In built up areas the initial phase of construction will involve demolition and site clearance. For HS2 this demolition will mostly take place around the Euston terminus and Birmingham station. In this part though I'd like to focus on the groundworks required in rural areas.
In rural areas the fertile earth is stored close to where it was excavated from, by doing this much of the ecology can be retained, this will help with the process of reestablishing wildlife habitats and returning agricultural land back to use.
The next phase of construction will involve deep excavation of cuttings and the building of embankments and structures. To do this excavators working in tandem with moxys will excavate and then move material from cuttings to areas where embankments will be built.
In this way it is possible to sculpt the landscape without having to move any earth off site by road or rail. Spoil from the excavation of tunnels can also be translocated to different parts of the site in this way.
The construction of a new grade separated junction at Norton Bridge is a good example how vast quantities of earth can be moved without the need to take any off site. In all 1 million tonnes of earth was moved in order to construct the 7.5km track and 11 bridges required for the project, yet non had to be taken off site.
This was achieved by creating a temporary road which extended along the length of the site, this haul road was then used to transport the material from where it was being excavated to where it was required. With 11 bridges constructed a lot of material was required in order to build approaches to overbridges. Earth was also used for landscaping either side of the line in order reduce the impact of the line on the landscape.
Of course for HS2 there will not a be a single 100km haul road, a project of this scale will be split up into sections, however withing each section it is likely that the same method of moving material will be employed.
The image above of a new overbridge constructed for the A556 project demonstrates where material is required in order to build new approaches. Earth was eventually built up on either side in order to build approaches for a new road overbridge.
It was suggested by a rural campaign group that millions of lorry loads will be required to take material off site by road, however the A556 and SAIP projects show that this needn't and will more than likely not be the case.
In part two I will discus the construction of bridge structures and look at how the impact on the existing road network can be minimised.
You can read part two here
Friday, 23 September 2016
Midland Metro growing ambition
Plans for a new light rail network were announced in 1988 and in November of that year the Bill to give powers to Centro to build the first line was deposited in Parliament. The initial line would follow much of the disused track bed of the Birmingham Snow Hill to Wolverhampton Low Level Line.
The Bill became an act of parliament a year later, however construction of the £145m line (at 1995 prices) did no begin until 1995 and was expected to open in August 1998. The consortium building the new line missed the deadline by 10 months and was forced to pay compensation.
The new line which was initially constructed between Wolverhampton St George's and Birmingham Snow Hill, with 23 stops in between finally opened in May 1999. It was the intention that this first line (Line 1) would be the first of several lines which would be built connecting Wolverhampton to Walsall and Birmingham City Centre to Birmingham Airport. Unfortunately however in 1997 Centro had to concede that it was unable to find funding for it's ambitious 3 line tram network.
In 2005 The Nation Audit Office concluded that line had not reached it's full potential of 8m passengers a year, instead the number of passengers using the line reached a plateau of around 5m which was still the case in 2015. The reason given was that line did not serve Birmingham City Centre, stopping instead just outside at Snow Hill Station.
The trams
The line was served by 16 T-69 trams built by AnsaldoBreda in Italy, each tram had a capacity of 156 passengers, 100 standing and 56 seated. The trams were refurbished in 2013, yet only a year later the trams were phased out as new replacement trams arrived.
Between 2014 and 2015 the entire fleet of T-69 trams was replaced with 21 Urbos 3 trams built by CAF in Spain. These vehicles had a capacity of 210, 156 standing and 54 seated. The £40m contract for the new trams included the construction of a new maintenance facility at Wednesbury.
Work on the extension began in June 2012 and it was hoped the the first services would be operating by March 2015. Unfortunately a series of delays meant that by December 2015 trams were only operating as far as Bull Street tram stop. It wasn't until May 2016 that trams finally began serving New Street.
Plans to extended the line from New Street to Centenary Square by 2019 are also at an advanced stage. Currently the line terminates at the junction of Stephenson St and Pinfold St. At this point trams turn back to make the return journey to Wolverhampton.
Stephenson St is currently the end of the line
It may have taken several decades but appears that the West Midlands may finally get a network worthy of it's size and importance.
Wednesday, 23 September 2015
Birmingham New Street redevelopment
On Sunday the 21st of September (2015) Network Rail finally unveiled the new enlarged concourse at Birmingham New Street station. The culmination of 5 years work requiring the effort of 1000 engineers working on site 24 hours a day, 7 days a week.
The new concourse which is the size of 13 Wimbledon centre courts is now bathed in light thanks to a new 3,300 square meter roof made from steel and ETFE (Ethylene Tetrafluoroethylene). The new roof introduces light to the station for the first time since the Brutalist concrete station was built to replace the original station in the 1960s.
In order to accommodate so many passengers, 30 new escalators and 15 new lifts have been installed, as well as 6 separate entry/exit points each with 10 ticket gates. Below the concourse all 12 platforms will be improved to allow better passenger flow and to open up the platform level making it seem less claustrophobic. Work was still underway on platform 5 on the day of my visit.
Some may question the £600m cost of the redevelopment, however I doubt that many will question that the station was in dire need of development or the success of the development itself. The building is striking and along with the Bullring it is a genuine architectural asset to the city. More importantly though the station now works for passengers and has enabled it to handle an ever increasing number of passengers.
- £750m Total development cost
- 1000 engineers worked 24/7 for 5 years
- 20,000 tonnes of concrete removed to create the atrium
- 3,300 square metre roof made from steel and ETFE
- 170,000 passengers use the station every day
- 10,000 lorry journeys saved by using rail to remove waste
- 30 new escalators installed
- 15 new lifts installed
- 13 centre courts at Wimbledon, the size of the new concourse
Latest blog post
HS2 Bridges and Viaducts Engineering Challenges
A version of this article was published in RAIL Magazine issue 1040 Construction of the 220km (140 mile) long HS2 route between London and ...
-
A version of this article was published in Rail Magazine in December 2021 As someone who lives on the Wirral and frequently travels to Nort...
-
Originally published in Rail Magazine issue 920 The Merseyrail network currently consists of 75 miles of railway, 6.5 miles of which are u...
-
A version of this article was Published in Rail Magazine , issue 999 The small village of Handsacre has recently become the focus of attenti...