Friday, 19 November 2021

IRP, Rail Revolution or Rail Betrayal? Northern Powerhouse Rail

On the 18th of November 2021 the Government published its long-awaited Integrated Rail Plan (IRP) that sets out how the Government will attempt to improve rail links across the North and Midlands. In this blog I hope to set out the main points from and unpick some of the claims made within the report.

This part, in a two part blog looks into the detail of the Northern Powerhouse Rail proposal. Part one looks at the HS2 East announcement and the possible implications of cancelling the eastern leg of HS2

Northern Powerhouse Rail (HS3)

Northern Powerhouse Rail is where things start to get a little more complicated, as far as I can tell the Government has rejected all 3 proposals put forward by Transport for the North, which were:

"Option 1 was a mixture of new-build high-speed line, covering roughly half the route from Liverpool to Leeds, and upgrades to the existing lines into Leeds (via Huddersfield) and Liverpool (via Warrington Bank Quay) for the rest of the route.

Option 2 was for an entirely new-build high-speed line between Leeds and Manchester, including a new station on the outskirts of Bradford; a new line from Warrington to Liverpool (with a parkway station at Warrington); and an underground Piccadilly station with a connection allowing it to be used for Sheffield services. •

Option 3 was the same as Option 2, but with a new central station underground at Warrington (still offering less convenient interchange to Bank Quay); and an underground station in the vicinity of the existing Bradford Interchange station.
"

Instead, the Government suggests a patchwork of upgrades, electrification and new sections of track from Liverpool to York.

Liverpool

Starting in Liverpool, it is suggested that there will be further works carried out to enhance Liverpool Lime Street station, presumably on top of the £500m that was spent in 2018 to improve the station's platform layout. However, it is difficult to see what the enhancement will achieve. Even after the £500m re-build the station will have no room for additional services beyond 2035.

HS2 phase 2a will introduce 2 additional trains per hour to London and Transport for Wales intend to introduce a new hourly service between Liverpool and Llandudno and an hourly service to Shrewsbury from Liverpool (with a service every 2 hours extended to Cardiff), that's on top of the hourly Chester to Liverpool via Runcorn service that was introduced in 2019. Beyond that, there is no scope to get any more trains into Liverpool Lime Street owing to the restrictions imposed by the 4 track approach into the station. Anyone who has taken the train to Liverpool Lime St will be aware of the deep cutting that the approach sits in, there is nothing in the IRP that suggests the Government will invest in new tracks into the station, which would be incredibly costly.

Liverpool to Manchester

Travelling out from Liverpool Lime St, HS2/NPR trains will use existing lines to Warrington Bank Quay, where new platforms would be constructed. The only way this could be achieved would be by using the Skelton Junction to Ditton Junction line which is currently used for freight. The line was primarily used by freight trains bringing coal to Fiddler's Ferry power station, but those flows ceased in 2020 when the power station closed. This line would have to be electrified and new low-level platforms constructed below the existing Warrington Bank Quay station. 

As you can see from the approximate map below, the line is curvaceous to say the least, meaning the approach into Warrington Bank Qual LL will be slow. The existing track alignment under Bank Quay is also curvaceous and would have to be re-aligned to allow for platforms to be built. 

Approximate possible route through Warrington using an existing line

 
Using this approach would mean that HS2 services bound for London that would otherwise have connected to HS2 at Crewe via Runcorn, would be diverted away from and therefore no longer serve from Runcorn. 

From Warrington Bank Quay there would be a new section of track connecting to HS2 phase 2b into Manchester. It had already been proposed that passive provision for new NPR/HS2 junctions be added to the bill for HS2 phase 2b. The junctions would be located West of Manchester Airport and would allow HS2 trains from Liverpool to head south to Crewe and then on to London, and NPR trains to head to Manchester using the tunnel that will be constructed as part of HS2 from Manchester Aiport to a new station to be constructed adjacent to Manchester Piccadilly. As The new HS2 station at Piccadilly will be a terminus this will mean NPR trains from Liverpool that would be travelling east would have to reverse, which is far from idea, as this will impact overall capacity and has the potential to impact service reliabilty.

Manchester to Leeds 

Heading east from Manchester the Government has suggested building a section of new railway from Piccadilly/HS2 to just east of Standedge tunnel, located approximately 10 miles from Huddersfield. From there NRP trains would continue over the existing line to Huddersfield and then on to Leeds. The Government suggests building 40 miles of new railway in total, from Warrington to Standedge tunnel, which would include the section of HS2 from just west of Manchester Airport to Manchester Piccadilly.

Northern Powerhouse Rail as set out in the IRP


Instead of building a new dedicated line that would have served a new through station at Bradford, the Government's watered-down plan is to invest in "significant improvements to the previous Transpennine Route Upgrade (TRU) plans", parts of which are already either underway or in the planning phase. Network Rail has already submitted plans to double the number of tracks and electrify the line from Huddersfield to Dewsbury.
 

The Government says it now plans to electrify the whole route, instal digital signalling throughout, provide significantly longer sections of three and four-tracking, and gauge upgrades to allow intermodal container freight services. 

Full electrification of the Transpennine route from Manchester to Leeds via Huddersfield was another promise the Government made in 2012 and was another promise the Government broke when it "paused" plans for electrification. The "pause" turned into cancellation of full electrification, with the Government instead instructing Network Rail to draw up plans for discontinuous electrification with scaled back upgrades of the Pennine route. 

The Government also says it will also electrify the route from Leeds to York with some new sections of four-tracking and it will upgrade and electrify the Leeds to Bradford section of the Calder Valley Line.

The IRP briefly mentions Hull, but any proposals fall under the banner of "Future possibilities". The IRP states "The Government has identified a core pipeline of schemes and any further schemes (such as Hull upgrades) will be subject to affordability, delivering commitments on time and to budget, and complementary investments being made. Given the scale of the IRP core portfolio, the Government considers that this – alongside the development work at Leeds and on the Midlands Rail Hub – needs to be the immediate focus for the supply chain and delivery bodies.". 

The IRP is littered with and phrases such as "core pipeline", "subject to affordability", "focussing on delivering", "undertake a study" and "optimal solution" which make it sound like the Government is doing something, whilst in reality it commits the Government to nothing. There's nothing in the IRP to suggest that it forms the basis of a single unified plan which will be looked at as a whole, it's more like an ad-hoc wish list of projects the Government would like to possibly see complete. An ad-hoc approach risks abstraction, whereby the business case for the whole cannot be considered, instead, each proposal must be judged by its own merits, which risks deliverability.  

Put simply the Government has worded the IRP in such a way that it doesn't have to commit to anything and certainly doesn't make any promises which can be broken later.

As far as "Northern Powerhouse Rail" goes, that's it, 40 miles of new track (including HS2 into Manchester) and a patchwork of upgrades which may or may not go ahead, subject to there being a positive business case.


Twitter - Facebook - Youtube

Thursday, 21 March 2019

Rail & the Liverpool City Region - The Track to Growth

This week I was fortunate enough to be invited to an event in Liverpool called “Rail & the Liverpool City Region - The Track to Growth”. The event was an opportunity for city, transport and business leaders to publicly give their full backing to Transport for the North's (TfN) Strategic Transport Plan (STP), and it was also an opportunity to celebrate 5 years since the formation of the Liverpool City Region, and the £340m that has been invested in rail over that period.

As part of the STP, Transport for the North have set out £40bn worth of investment in rail which amongst other things will see Liverpool connected to HS2 and Manchester by a dedicated 2 track high speed line. This is something the city has been demanding since the route of phase 2 between the West Midlands and North West was announced. Whilst business and political leaders have been supportive of HS2, with benefits coming to the region from 2026, they were never fully satisfied with Liverpool's connection to HS2 being as far south as Crewe.

Rather than seeing HS2 connectivity as an insurmountable challenge the LCR and TfN have worked together to see how HS2 could be extended and integrated with a new line which provides Liverpool with direct connectivity to HS2, but also to Northern Power House Rail heading east to Manchester and Leeds.

Also this week a proposal was put forward for a new railway station to be built within Liverpool city centre, which would be connected to NPR. The new station would ideally have platforms 400m in length to take full advantage of the new longer trains that will be used on the HS2 core network. Currently Liverpool Lime St is limited to trains of around 260m in length (the length of an 11 car Pendolino). Lime St is also about to reach the limits of its capacity, this despite the recent the upgrade to the track approaching the station and the construction of a new platform. Very soon new services to Scotland and to Chester via Halton curve will consume the new capacity created. HS2 itself will also introduce 2 new services each hour to Euston from 2026. Therefore city leaders say that it is vital that Liverpool gains a new station and dedicated connection to HS2 and Manchester via NPR.





LCR estimates the HS2 link could provide £15bn worth of economic benefits and attract an additional 3.9m visitors per year to the region. Claire McColgan MBE Director of Culture Liverpool spelled out just how important having good transport links is to the tourism economy in the region, but also how vital tourism and culture are to the region's economy. Ms McColgan made it clear that event organisers want to host events in the LCR “because they know that the city transport sectors work together”. Pointing to success stories such as the Giants Spectacular last year which attracted 1.4m visitors across Liverpool and the Wirral, and the sailing of the 3 Queens along the River Mersey, which saw 1m people line the River on both sides to see the ships sail in.

Liverpool City Region

The event wasn't focused solely on the STP, it was also a good opportunity to celebrate some of the success stories over the past 5 year, since the formation of the LCR. The LCR led by by Metro Mayor Steve Rotheram brings together Liverpool City Region’s six local authorities – Halton, Knowsley, Liverpool, Sefton, St Helens and Wirral working in cooperation to tackle issues that face the region. Not just transport for but housing, skills and Energy. In terms of transport though the LCR was able to bring together local transport plans, Network Rail's RUS and the needs of businesses to identify key infrastructure improvements that were required to help unlock the potential of the region.

The result of the collaborative approach was a £340m package of measures that would improve rail connections across the region and would help to enable new services and improve reliability. The largest of the measures was the work undertaken at Liverpool Lime St, but improvements were not focused solely on the city centre. A long held aspiration to re-instate bi-directional running at Halton Curve linking the North Cheshire railway to the WCML at Runcon has been realised, and a brand new station named Maghull North has been constructed.

Metro Mayor Steve Rotheram


Shortages of rolling stock has meant that services using the now complete Halton Curve have been delayed, but it is hoped that Transport for Wales Rail will begin to operate services between Chester and Liverpool, calling Helsby, Frodsham, Runcorn and Liverpool South Parkway in May this year.

Skills

It is clear that Liverpool transport, business and political leaders fully support HS2 and the TfN STP, but a word cropped up again which has the potential to threaten any future investment, that word was skills. Echoing the challenges outlined by the NRIL – Building New Railways report, Northern Powerhouse Rail Director Tim Wood made it clear that "the major risk to the programme is not money, it is skills” (or the lack there of). This is something I have written about for many years, in fact I first wrote about the skills gap back in 2015 when it emerged that GWML electrification was going to be delivered late and over budget, and that electrification of the Transpennine route was to be "paused".

What was true in 2015, unfortunately is still true today, we simple do not have enough skilled engineers in the UK to undertake the work that is necessary to get the North moving. It is frustrating in a number of ways, one because it seems as if people read on a daily basis in the main stream media, that the government should cancel HS2 and invest in the North and how it will solve all of our problems, but it just wont. And it's frustrating because we should be getting on with building infrastructure in the North, but we can't, not yet.

Let me give a example of why cancelling HS2 today would not improve railways tomorrow. In simplified terms HS2 is new railway and as such is moving towards the heavy civil engineering phase in which earth is moved, tunnels are excavated and structures are built. This requires a certain type of engineering skill set, such as earth work contractors and tunnelling experts. If they stopped work today and were moved up north to build something, what would it be? There are no detailed plans for NPR, no shovel ready civil engineering projects for them to begin work on.

What people might be thinking when they say “improvements” are upgrades, which is understandable, but those tunnellers and earth work engineers aren't correctly skilled to then start upgrading the railways. Most of the egineers who are correctly skilled to upgrade our railways are already doing so. Tens of thousands of them working tirelessly usually at night to improve Britian's railways.

Now I know it is probably a bit over simplified, but it does demonstrate that you simple can't down tools on one project and start another, and especially not by just throwing money at it.

The skills gap is going to take years to fill, and while good progress is being made with universities working in cooperation with TfN and NRIL and the formation of National High Speed Rail college, there is still a long way to go. Getting children ready to become the engineers of tomorrow needs to begin in primary and secondary schools.

We cannot allow there to be another lost generation like mine, which was told university is the only avenue available to you if you want any sort of career. I know in my school careers in science, education and IT were promoted, but the idea that you could have a successful career in engineering just never came up.


One last word on HS2, it was clear from yesterday's event that the LCR and TFN who represent 19 local transport authorities from across North thoroughly reject the notion that we should scrap HS2 and invest in the North instead. Tim Wood spelled out the message from TfN again "Let me be clear, we absolutely need HS2". The simple fact is we need both HS2 and NPR.





Follow me on Twitter and Facebook

 For more information 
e-mail info@EngineeringBlog.co.uk

Latest blog post

HS2 Bridges and Viaducts Engineering Challenges

A version of this article was published in RAIL Magazine issue 1040 Construction of the 220km (140 mile) long HS2 route between London and ...